Stonecrop Solar

PJM queue ID AG1-320

Queue IDAG1-320
Project nameStonecrop Solar
Status (as published)EP
SubstationHodgenville-Stephensburg
Point of interconnectionHodgenville-Stephensburg 69 kV
CountyHardin
StateKY
Voltage69 kV
Capacity54.8 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2029-12-31
Source datasetcycle

Additional filed fields

DeveloperCPV Stonecrop Solar, LLC
Transmission OwnerEKPC
Project TypeGeneration Interconnection
CycleTC1
StageFINAL AGREEMENT
Mw Energy82.0
Mw Capacity54.8
Mfo82.0
Submitted Date9/30/2020
Last Updated2/10/2026