Hardin, KY interconnection queue
1 active project totalling 54.8 MW in the PJM queue, plus 13 with terminal status (shown greyed).
1active projects
54.8active MW
14total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AH1-016 | Central Hardin 138 kV | 138 | 108 | Solar | Withdrawn |
| AF2-090 | Central Hardin 138 kV | 138 | 73.6 | Solar | Withdrawn |
| AF2-391 | Central Hardin 69 kV | 69 | 72 | Hybrid | Withdrawn |
| AG1-320 | Stonecrop Solar | 69 | 54.8 | Solar | EP |
| AF2-260 | Stephensburg-Central Hardin 69 kV | 69 | 53 | Solar | Withdrawn |
| AF2-309 | Central Hardin-Stephensburg 69 kV | 69 | 42 | Solar | Withdrawn |
| AG1-491 | Central Hardin 69 kV | 69 | 42 | Hybrid | Withdrawn |
| AF2-246 | Stephensburg 69 kV | 69 | 38.7 | Solar | Withdrawn |
| AG1-096 | Rineyville 69 kV | 69 | 36.7 | Hybrid | Withdrawn |
| AG2-183 | Not reported | n/r | 30 | Solar | Withdrawn |
| AF2-308 | Central Hardin-Stephensburg 69 kV | 69 | 28 | Battery | Withdrawn |
| AG2-549 | Rineyville 69 kV | 69 | 26.7 | Solar | Withdrawn |
| AI2-376 | Central Hardin-Stephensburg 69 kV | 69 | 21.8 | Solar | Withdrawn |
| AG2-662 | Stephensburg - Central Hardin 69 kV | 69 | 0 | Battery | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.