Greenfield CSG 1
PJM queue ID AG1-253
Greenfield CSG 1 (AG1-253) is listed in the PJM interconnection queue as a 2.7 MW solar project in Erie County, PA. The filing names Erie East-Union City as its point of interconnection. PJM lists its status as “Suspended”, with a target commercial operation date of May 30, 2025.
| Queue ID | AG1-253 |
|---|---|
| Project name | Greenfield CSG 1 |
| Status (as published) | Suspended |
| Substation | Erie East-Union City |
| Point of interconnection | Erie East-Union City 34.5 kV |
| County | Erie |
| State | PA |
| Voltage | 34.5 kV |
| Capacity | 2.7 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2025-05-30 |
| Source dataset | serial |
Same substation and county
Erie, PA: 42 requests in the PJM queue, 7 active totaling 1,217.4 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 4 |
| MW capacity | 2.7 |
| MFO | 4 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.