Brunswick Battery Storage

PJM queue ID AG1-153

Queue IDAG1-153
Project nameBrunswick Battery Storage
Status (as published)UC
SubstationHeritage
Point of interconnectionHeritage 500 kV
CountyBrunswick
StateVA
Voltage500 kV
Capacity30 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2031-07-28
Source datasetcycle

Additional filed fields

DeveloperVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StageFINAL AGREEMENT
Mw Energy75.0
Mw Capacity30.0
Mfo75.0
Submitted Date9/10/2020
Last Updated8/12/2026