Wild Rose Solar Project

PJM queue ID AG1-124

Queue IDAG1-124
Project nameWild Rose Solar Project
Status (as published)EP
SubstationRiverville - Gladstone
Point of interconnectionRiverville - Gladstone 138 kV
CountyNelson
StateVA
Voltage138 kV
Capacity53 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2030-11-15
Source datasetcycle

Additional filed fields

DeveloperWild Rose Solar Project, LLC
Transmission OwnerAEP
Project TypeGeneration Interconnection
CycleTC1
StageFINAL AGREEMENT
Mw Energy90.0
Mw Capacity53.01
Mfo90.0
Submitted Date8/31/2020
Last Updated2/26/2026