PJM queue ID AG1-124
Wild Rose Solar Project (AG1-124) is listed in the PJM interconnection queue as a 53 MW solar project in Nelson County, VA. The filing names Riverville - Gladstone as its point of interconnection. PJM lists its status as “EP”, with a target commercial operation date of November 15, 2030.
| Queue ID | AG1-124 |
|---|---|
| Project name | Wild Rose Solar Project |
| Status (as published) | EP |
| Substation | Riverville - Gladstone |
| Point of interconnection | Riverville - Gladstone 138 kV |
| County | Nelson |
| State | VA |
| Voltage | 138 kV |
| Capacity | 53 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2030-11-15 |
| Source dataset | cycle |
Same substation and county
Nelson, VA: 5 requests in the PJM queue, 1 active totaling 53 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Wild Rose Solar Project, LLC |
|---|---|
| Transmission owner | AEP |
| Project type | Generation Interconnection |
| Cycle | TC1 |
| Stage | FINAL AGREEMENT |
| MW energy | 90.0 |
| MW capacity | 53.01 |
| MFO | 90.0 |
| Submitted date | 8/31/2020 |
| Last updated | 2/26/2026 |