Bright Mountain Solar
PJM queue ID AG1-066
Bright Mountain Solar (AG1-066) is listed in the PJM interconnection queue as a 48 MW solar project in Perry County, KY. The filing names Bonnyman as its point of interconnection. PJM lists its status as “Engineering and Procurement”, with a target commercial operation date of January 22, 2028.
| Queue ID | AG1-066 |
|---|---|
| Project name | Bright Mountain Solar |
| Status (as published) | Engineering and Procurement |
| Substation | Bonnyman |
| Point of interconnection | Bonnyman 69 kV |
| County | Perry |
| State | KY |
| Voltage | 69 kV |
| Capacity | 48 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2028-01-22 |
| Source dataset | serial |
Same substation and county
Perry, KY: 11 requests in the PJM queue, 1 active totaling 48 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 80 |
| MW capacity | 48 |
| MFO | 80 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.