Fairhaven Battery Energy Storage System
PJM queue ID AG1-063
Fairhaven Battery Energy Storage System (AG1-063) is listed in the PJM interconnection queue as a 0.7 MW battery project in Anne Arundel County, MD. The filing names Fairhaven 13,8 kV as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of September 30, 2024.
| Queue ID | AG1-063 |
|---|---|
| Project name | Fairhaven Battery Energy Storage System |
| Status (as published) | In Service |
| Substation | Fairhaven 13,8 kV |
| Point of interconnection | Fairhaven 13,8 kV |
| County | Anne Arundel |
| State | MD |
| Voltage | Not reported |
| Capacity | 0.7 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2024-09-30 |
| Source dataset | serial |
Same substation and county
Anne Arundel, MD: 29 requests in the PJM queue, 11 active totaling 1,322.7 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 2.5 |
| MW capacity | 0.7 |
| MFO | 2.5 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.