Substation Scout

Walker Solar Two

PJM queue ID AF2-361

Queue IDAF2-361
Project nameWalker Solar Two
Status (as published)Under Construction
SubstationMifflintown Tap
Point of interconnectionMifflintown Tap 69 kV
CountyJuniata
StatePA
Voltage69 kV
Capacity35 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2026-09-19
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy80
Mw Capacity35
Mfo80

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.