Juniata, PA interconnection queue

3 active projects totalling 48 MW in the PJM queue, plus 2 with terminal status (shown greyed).

3active projects
48active MW
5total filed
Queue IDProjectkVMWResourceStatus
AF2-361 Walker Solar Two 69 35 Solar Under Construction
C11 Mifflintown 69kV 69 9.9 Gas Withdrawn
AE2-060 Cottontail Solar 5 aka Walker Solar 69 8.4 Solar In Service
AG2-484 Mifflintown Bus-Mifflintown Tap 69 kV II 69 4.6 Solar Active
AH1-111 Walker 12 kV 12 3 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.