Winterberry Solar (AF2-077) is listed in the PJM interconnection queue as a 12 MW solar project in Gloucester County, VA. The filing names White Marsh as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of August 14, 2024.

Queue IDAF2-077
Project nameWinterberry Solar
Status (as published)In Service
SubstationWhite Marsh
Point of interconnectionWhite Marsh 34.5 kV
CountyGloucester
StateVA
Voltage34.5 kV
Capacity12 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2024-08-14
Source datasetserial

Same substation and county

White Marsh substation: 3 requests in the PJM queue, 1 active totaling 12 MW.

Queue IDProjectMWResourceStatus
AI2-318White Marsh 34.5 kV12.8BatteryWithdrawn
AG1-102White Marsh 34.5 kV6.2BatteryWithdrawn

Gloucester, VA: 15 requests in the PJM queue, 7 active totaling 133.2 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy20
MW capacity12
MFO20

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first