Randolph Solar

PJM queue ID AF2-042

Queue IDAF2-042
Project nameRandolph Solar
Status (as published)UC
SubstationClover-Rawlings
Point of interconnectionClover-Rawlings 500 kV
CountyHalifax
StateVA
Voltage500 kV
Capacity300 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2032-12-31
Source datasetcycle

Additional filed fields

DeveloperVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StageFINAL AGREEMENT
Mw Energy500.0
Mw Capacity300.0
Mfo500.0
Submitted Date12/9/2019
Last Updated8/13/2026