Randolph Solar
PJM queue ID AF2-042
Randolph Solar (AF2-042) is listed in the PJM interconnection queue as a 300 MW solar project in Halifax County, VA. The filing names Clover-Rawlings as its point of interconnection. PJM lists its status as “UC”, with a target commercial operation date of December 31, 2032.
| Queue ID | AF2-042 |
|---|---|
| Project name | Randolph Solar |
| Status (as published) | UC |
| Substation | Clover-Rawlings |
| Point of interconnection | Clover-Rawlings 500 kV |
| County | Halifax |
| State | VA |
| Voltage | 500 kV |
| Capacity | 300 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2032-12-31 |
| Source dataset | cycle |
Same substation and county
Clover-Rawlings substation: 4 requests in the PJM queue, 2 active totaling 420 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AG2-077 | Clover-Rawlings 500 kV | 120 | Solar | Active |
| AG1-357 | Clover-Rawlings 500 kV | 120 | Solar | Withdrawn |
| AF1-246 | Clover-Rawlings 500 kV | 42 | Solar | Withdrawn |
Halifax, VA: 57 requests in the PJM queue, 25 active totaling 1,315.8 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) |
|---|---|
| Transmission owner | Dominion |
| Project type | Generation Interconnection |
| Cycle | TC1 |
| Stage | FINAL AGREEMENT |
| MW energy | 500.0 |
| MW capacity | 300.0 |
| MFO | 500.0 |
| Submitted date | 12/9/2019 |
| Last updated | 8/13/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.