South Orchard
PJM queue ID AF1-239
South Orchard (AF1-239) is listed in the PJM interconnection queue as a 12 MW battery project in Cumberland County, NJ. The filing names Sherman Ave - West Vineland as its point of interconnection. PJM lists its status as “Engineering and Procurement”, with a target commercial operation date of June 1, 2028.
| Queue ID | AF1-239 |
|---|---|
| Project name | South Orchard |
| Status (as published) | Engineering and Procurement |
| Substation | Sherman Ave - West Vineland |
| Point of interconnection | Sherman Ave - West Vineland 69 kV |
| County | Cumberland |
| State | NJ |
| Voltage | 69 kV |
| Capacity | 12 MW |
| Resource (as published) | Storage |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2028-06-01 |
| Source dataset | serial |
Same substation and county
Sherman Ave - West Vineland substation: 2 requests in the PJM queue, 2 active totaling 32 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AF1-238 | South Orchard | 20 | Battery | EP |
Cumberland, NJ: 94 requests in the PJM queue, 15 active totaling 1,148.7 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 30 |
| MW capacity | 12 |
| MFO | 80 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.