Springwater Solar
PJM queue ID AF1-228
Springwater Solar (AF1-228) is listed in the PJM interconnection queue as a 93 MW solar project in Madison County, OH. The filing names Beatty-Greene as its point of interconnection. PJM lists its status as “Under Construction”, with a target commercial operation date of August 31, 2027.
| Queue ID | AF1-228 |
|---|---|
| Project name | Springwater Solar |
| Status (as published) | Under Construction |
| Substation | Beatty-Greene |
| Point of interconnection | Beatty-Greene 345 kV |
| County | Madison |
| State | OH |
| Voltage | 345 kV |
| Capacity | 93 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2027-08-31 |
| Source dataset | serial |
Same substation and county
Beatty-Greene substation: 2 requests in the PJM queue, 2 active totaling 490.3 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AE2-148 | Fox Squirrel Solar | 397.3 | Solar | In Service |
Madison, OH: 40 requests in the PJM queue, 11 active totaling 3,530 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 155 |
| MW capacity | 93 |
| MFO | 155 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.