Substation Scout

Henry County Solar

PJM queue ID AF1-205

Henry County Solar (AF1-205) is listed in the PJM interconnection queue as a 24 MW solar project in Henry County, OH. The filing names Napoleon Muni as its point of interconnection. PJM lists its status as “Suspended”, with a target commercial operation date of August 1, 2026.

Queue IDAF1-205
Project nameHenry County Solar
Status (as published)Suspended
SubstationNapoleon Muni
Point of interconnectionNapoleon Muni 138 kV
CountyHenry
StateOH
Voltage138 kV
Capacity24 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2026-08-01
Source datasetserial

Same substation and county

Napoleon Muni substation: 3 requests in the PJM queue, 1 active totaling 24 MW.

Queue IDProjectMWResourceStatus
AH2-288Napoleon Muni 138 kV82.4BatteryWithdrawn
AG1-319Napoleon Muni 138 kV39SolarWithdrawn

Henry, OH: 11 requests in the PJM queue, 1 active totaling 24 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy40
MW capacity24
MFO40

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.