PJM queue ID AF1-198

Blossburg Station Unit 1 (AF1-198) is listed in the PJM interconnection queue as a 2.5 MW gas project in Tioga County, PA. The filing names Blossburg #1 CT as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of September 30, 2023.

Queue IDAF1-198
Project nameBlossburg Station Unit 1
Status (as published)In Service
SubstationBlossburg #1 CT
Point of interconnectionBlossburg #1 CT 34.5 kV
CountyTioga
StatePA
Voltage34.5 kV
Capacity2.5 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2023-09-30
Source datasetserial

Same substation and county

Tioga, PA: 21 requests in the PJM queue, 1 active totaling 2.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy2.5
MW capacity2.5
MFO22.5

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first