Hamilton Station
PJM queue ID AF1-194
Hamilton Station (AF1-194) is listed in the PJM interconnection queue as a 1 MW project in York County, PA. The filing names Hamilton CT1 as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of September 30, 2023.
| Queue ID | AF1-194 |
|---|---|
| Project name | Hamilton Station |
| Status (as published) | In Service |
| Substation | Hamilton CT1 |
| Point of interconnection | Hamilton CT1 115 kV |
| County | York |
| State | PA |
| Voltage | 115 kV |
| Capacity | 1 MW |
| Resource (as published) | Oil |
| Resource category | Other (normalized for filtering) |
| Target commercial operation | 2023-09-30 |
| Source dataset | serial |
Same substation and county
York, PA: 76 requests in the PJM queue, 22 active totaling 2,107.2 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 1 |
| MW capacity | 1 |
| MFO | 27 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.