Juliet Energy
PJM queue ID AF1-064
Juliet Energy (AF1-064) is listed in the PJM interconnection queue as a 33.4 MW solar project in Wood County, OH. The filing names Weston as its point of interconnection. PJM lists its status as “Partially in Service - Under Construction”, with a target commercial operation date of May 29, 2027.
| Queue ID | AF1-064 |
|---|---|
| Project name | Juliet Energy |
| Status (as published) | Partially in Service - Under Construction |
| Substation | Weston |
| Point of interconnection | Weston 69 kV |
| County | Wood |
| State | OH |
| Voltage | 69 kV |
| Capacity | 33.4 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2027-05-29 |
| Source dataset | serial |
Same substation and county
Wood, OH: 19 requests in the PJM queue, 7 active totaling 887.6 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 50 |
| MW capacity | 33.4 |
| MFO | 50 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.