Substation Scout

Hamilton Road Solar

PJM queue ID AF1-023

Hamilton Road Solar (AF1-023) is listed in the PJM interconnection queue as a 8.4 MW solar project in Monmouth County, NJ. The filing names Atlantic-Red Bank II as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of September 1, 2023.

Queue IDAF1-023
Project nameHamilton Road Solar
Status (as published)In Service
SubstationAtlantic-Red Bank II
Point of interconnectionAtlantic-Red Bank 34 kV II
CountyMonmouth
StateNJ
Voltage34 kV
Capacity8.4 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2023-09-01
Source datasetserial

Same substation and county

Monmouth, NJ: 79 requests in the PJM queue, 18 active totaling 46.1 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy0
MW capacity8.4
MFO20

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.