Madison Solar

PJM queue ID AE2-308

Queue IDAE2-308
Project nameMadison Solar
Status (as published)EP
SubstationThree Forks-Dale
Point of interconnectionThree Forks-Dale 138 kV
CountyMadison
StateKY
Voltage138 kV
Capacity60 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2029-01-31
Source datasetcycle

Additional filed fields

DeveloperAEUG Madison Solar, LLC
Transmission OwnerEKPC
Project TypeGeneration Interconnection
CycleTC1
StageFINAL AGREEMENT
Mw Energy100.0
Mw Capacity60.0
Mfo100.0
Submitted Date3/29/2019
Last Updated2/9/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.