Gladys Solar

PJM queue ID AE2-283

Queue IDAE2-283
Project nameGladys Solar
Status (as published)EP
SubstationGladys-Stone Mill
Point of interconnectionGladys-Stone Mill 69 kV
CountyCampbell
StateVA
Voltage69 kV
Capacity28 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2031-03-01
Source datasetcycle

Additional filed fields

DeveloperGladys Solar, LLC
Transmission OwnerDominion
Project TypeGeneration Interconnection
CycleTC1
StageFINAL AGREEMENT
Mw Energy53.0
Mw Capacity28.0
Mfo53.0
Submitted Date3/29/2019
Last Updated6/18/2026