Substation Scout

Panther Grove 2

PJM queue ID AE2-255

Panther Grove 2 (AE2-255) is listed in the PJM interconnection queue as a 25 MW wind project in Woodford County, IL. The filing names Molecreek as its point of interconnection. PJM lists its status as “Under Construction”, with a target commercial operation date of January 18, 2028.

Queue IDAE2-255
Project namePanther Grove 2
Status (as published)Under Construction
SubstationMolecreek
Point of interconnectionMolecreek 345 kV
CountyWoodford
StateIL
Voltage345 kV
Capacity25 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Target commercial operation2028-01-18
Source datasetserial

Same substation and county

Woodford, IL: 18 requests in the PJM queue, 6 active totaling 279.4 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy100
MW capacity25
MFO400

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.