Substation Scout

Woodford, IL interconnection queue

6 active projects totalling 279.4 MW in the PJM queue, plus 12 with terminal status (shown greyed).

6active projects
279.4active MW
18total filed
Queue IDProjectkVMWResourceStatus
AG1-379 Minonk 345 kV 345 137.2 Solar Withdrawn
AI2-317 Powertn - Goodings Grove 345 kV (CIR Increase) 345 133 Wind Withdrawn
AI2-234 Mole Creek 345kV (CIR Increase) 345 92.4 Wind Withdrawn
C01-1274 Mole Creek TSS 908 345 kV 345 92.4 Wind Active
AI2-315 Mole Creek 345 kV 345 90 Wind Withdrawn
AE1-113 Panther Grove 2 345 66 Wind Under Construction
AI2-245 TSS 968 345 kV (CIR Increase) 345 55.2 Solar Withdrawn
AH1-361 Minonk 345 kV 345 50 Battery Withdrawn
AE1-163 Panther Grove Wind 345 49 Wind Under Construction
O50 Minonk Wind Farm 345 40 Wind In Service
K07_CE20 Benson Wind Farm n/r 31.6 Wind Withdrawn
AI2-314 Molecreek 345kV (CIR Increase) 345 27 Wind Withdrawn
W3-052 Tazewell-Kendall 345kV 345 26 Wind Withdrawn
AE2-255 Panther Grove 2 345 25 Wind Under Construction
O73 Benson 345kV 345 20 Wind Withdrawn
AI2-316 Powerton 345 kV (CIR increase) 345 19 Wind Withdrawn
AE2-281 Panther Grove Wind 345 7 Wind Under Construction
U1-011 Minonk II 34.5kV 34.5 2.6 Wind Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.