Woodford, IL interconnection queue
6 active projects totalling 279.4 MW in the PJM queue, plus 12 with terminal status (shown greyed).
6active projects
279.4active MW
18total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AG1-379 | Minonk 345 kV | 345 | 137.2 | Solar | Withdrawn |
| AI2-317 | Powertn - Goodings Grove 345 kV (CIR Increase) | 345 | 133 | Wind | Withdrawn |
| AI2-234 | Mole Creek 345kV (CIR Increase) | 345 | 92.4 | Wind | Withdrawn |
| C01-1274 | Mole Creek TSS 908 345 kV | 345 | 92.4 | Wind | Active |
| AI2-315 | Mole Creek 345 kV | 345 | 90 | Wind | Withdrawn |
| AE1-113 | Panther Grove 2 | 345 | 66 | Wind | Under Construction |
| AI2-245 | TSS 968 345 kV (CIR Increase) | 345 | 55.2 | Solar | Withdrawn |
| AH1-361 | Minonk 345 kV | 345 | 50 | Battery | Withdrawn |
| AE1-163 | Panther Grove Wind | 345 | 49 | Wind | Under Construction |
| O50 | Minonk Wind Farm | 345 | 40 | Wind | In Service |
| K07_CE20 | Benson Wind Farm | n/r | 31.6 | Wind | Withdrawn |
| AI2-314 | Molecreek 345kV (CIR Increase) | 345 | 27 | Wind | Withdrawn |
| W3-052 | Tazewell-Kendall 345kV | 345 | 26 | Wind | Withdrawn |
| AE2-255 | Panther Grove 2 | 345 | 25 | Wind | Under Construction |
| O73 | Benson 345kV | 345 | 20 | Wind | Withdrawn |
| AI2-316 | Powerton 345 kV (CIR increase) | 345 | 19 | Wind | Withdrawn |
| AE2-281 | Panther Grove Wind | 345 | 7 | Wind | Under Construction |
| U1-011 | Minonk II 34.5kV | 34.5 | 2.6 | Wind | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.