Substation Scout

Powell Creek Solar

PJM queue ID AE2-072

Powell Creek Solar (AE2-072) is listed in the PJM interconnection queue as a 90 MW solar project in Putnam County, OH. The filing names East Leipsic-Richland as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 2, 2025.

Queue IDAE2-072
Project namePowell Creek Solar
Status (as published)In Service
SubstationEast Leipsic-Richland
Point of interconnectionEast Leipsic-Richland 138 kV
CountyPutnam
StateOH
Voltage138 kV
Capacity90 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2025-06-02
Source datasetserial

Same substation and county

Putnam, OH: 10 requests in the PJM queue, 4 active totaling 169 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy150
MW capacity90
MFO150

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.