Substation Scout

Glover Creek Solar

PJM queue ID AE2-071

Glover Creek Solar (AE2-071) is listed in the PJM interconnection queue as a 21 MW solar project in Metcalfe County, KY. The filing names Patton Rd-Summer Shade as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of April 30, 2024.

Queue IDAE2-071
Project nameGlover Creek Solar
Status (as published)In Service
SubstationPatton Rd-Summer Shade
Point of interconnectionPatton Rd-Summer Shade 69 kV
CountyMetcalfe
StateKY
Voltage69 kV
Capacity21 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2024-04-30
Source datasetserial

Same substation and county

Patton Rd-Summer Shade substation: 3 requests in the PJM queue, 2 active totaling 33 MW.

Queue IDProjectMWResourceStatus
AF1-203Glover Creek Solar12SolarIn Service
AI2-327Patton Rd-Summer Shade 69 kV19.9SolarWithdrawn

Metcalfe, KY: 10 requests in the PJM queue, 3 active totaling 96.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy35
MW capacity21
MFO35

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first