Substation Scout

Niagara Power Plant Dam

PJM queue ID AE1-176

Queue IDAE1-176
Project nameNiagara Power Plant Dam
Status (as published)In Service
SubstationRoanoke-Vinton (Niagara Hydro)
Point of interconnectionRoanoke-Vinton 12 kV (Niagara Hydro)
CountyRoanoke
StateVA
Voltage12 kV
Capacity2.4 MW
Resource (as published)Hydro
Resource categoryHydro (normalised for filtering)
Target commercial operation2020-06-01
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy2.4
Mw Capacity2.4
Mfo2.4