Substation Scout

Roanoke, VA interconnection queue

1 active project totalling 2.4 MW in the PJM queue, plus 5 with terminal status (shown greyed).

1active projects
2.4active MW
6total filed
Queue IDProjectkVMWResourceStatus
C01-1679 Matt Funk 345 kV 345 75 Battery Withdrawn
AG2-310 Matt Funk 138 kV 138 70 Battery Withdrawn
P53 Bent Mtn. 138kV 138 16.2 Wind Withdrawn
AA1-007 Smith Gap Regional Landfill n/r 6 Gas Withdrawn
W1-036 Central Solar Park 138 5.9 Wind Withdrawn
AE1-176 Niagara Power Plant Dam 12 2.4 Hydro In Service

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.