Substation Scout

Capon Bridge Solar

PJM queue ID AE1-109

Capon Bridge Solar (AE1-109) is listed in the PJM interconnection queue as a 8.7 MW solar project in Hampshire County, WV. The filing names Frenchs Mill as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of July 31, 2024.

Queue IDAE1-109
Project nameCapon Bridge Solar
Status (as published)In Service
SubstationFrenchs Mill
Point of interconnectionFrenchs Mill 34 kV
CountyHampshire
StateWV
Voltage34 kV
Capacity8.7 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2024-07-31
Source datasetserial

Same substation and county

Hampshire, WV: 6 requests in the PJM queue, 3 active totaling 68.8 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy20
MW capacity8.7
MFO20

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.