Aspen Road Solar

PJM queue ID AE1-071

Aspen Road Solar (AE1-071) is listed in the PJM interconnection queue as a 62.1 MW solar project in Franklin County, PA. The filing names Shade Gap-Roxbury as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of March 8, 2025.

Queue IDAE1-071
Project nameAspen Road Solar
Status (as published)In Service
SubstationShade Gap-Roxbury
Point of interconnectionShade Gap-Roxbury 115 kV
CountyFranklin
StatePA
Voltage115 kV
Capacity62.1 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2025-03-08
Source datasetserial

Same substation and county

Franklin, PA: 80 requests in the PJM queue, 20 active totaling 384.3 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy100.1
MW capacity62.1
MFO100.1

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.