Substation Scout

Guernsey Power Station

PJM queue ID AD2-189

Guernsey Power Station (AD2-189) is listed in the PJM interconnection queue as a 186 MW gas project in Guernsey County, OH. The filing names Kammer-Vassell as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 31, 2022.

Queue IDAD2-189
Project nameGuernsey Power Station
Status (as published)In Service
SubstationKammer-Vassell
Point of interconnectionKammer-Vassell 765kV
CountyGuernsey
StateOH
Voltage765 kV
Capacity186 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2022-12-31
Source datasetserial

Same substation and county

Kammer-Vassell substation: 3 requests in the PJM queue, 3 active totaling 1,836 MW.

Queue IDProjectMWResourceStatus
AB2-067Guernsey Power Station1,100GasIn Service
AC1-044Guernsey Power Station550GasIn Service

Guernsey, OH: 6 requests in the PJM queue, 4 active totaling 1,866.7 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy225
MW capacity186
MFO1875

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.