Guernsey, OH interconnection queue
4 active projects totalling 1,866.7 MW in the PJM queue, plus 2 with terminal status (shown greyed).
4active projects
1,866.7active MW
6total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AB2-067 | Guernsey Power Station | 765 | 1,100 | Gas | In Service |
| AC1-044 | Guernsey Power Station | 765 | 550 | Gas | In Service |
| AD2-189 | Guernsey Power Station | 765 | 186 | Gas | In Service |
| AE1-227 | Recreation Solar | 69 | 30.7 | Solar | Suspended |
| AC1-124 | Harryette 12kV | 12 | 0 | Battery | Withdrawn |
| AC1-125 | Harryette 12kV | 12 | 0 | Battery | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.