Spectrum Solar

PJM queue ID AD2-058

Queue IDAD2-058
Project nameSpectrum Solar
Status (as published)In Service
SubstationSt. Barnabas
Point of interconnectionSt. Barnabas 13 kV
CountyPrince George's
StateMD
Voltage13 kV
Capacity2.4 MW
Resource (as published)Solar
Resource categorySolar (normalised for filtering)
Target commercial operation2022-06-03
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy5.6
Mw Capacity2.38
Mfo5.6