Substation Scout

Spectrum Solar

PJM queue ID AD2-058

Spectrum Solar (AD2-058) is listed in the PJM interconnection queue as a 2.4 MW solar project in Prince George's County, MD. The filing names St. Barnabas as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 3, 2022.

Queue IDAD2-058
Project nameSpectrum Solar
Status (as published)In Service
SubstationSt. Barnabas
Point of interconnectionSt. Barnabas 13 kV
CountyPrince George's
StateMD
Voltage13 kV
Capacity2.4 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2022-06-03
Source datasetserial

Same substation and county

St. Barnabas substation: 3 requests in the PJM queue, 1 active totaling 2.4 MW.

Queue IDProjectMWResourceStatus
AE2-336St. Barnabas 13 kV1.9SolarWithdrawn
AE2-337St. Barnabas 13 kV1SolarWithdrawn

Prince George's, MD: 57 requests in the PJM queue, 14 active totaling 3,551.2 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy5.6
MW capacity2.38
MFO5.6

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first