Phillips Island CT1, CT2, CT3, and ST4
PJM queue ID AD1-097
Phillips Island CT1, CT2, CT3, and ST4 (AD1-097) is listed in the PJM interconnection queue as a 34.8 MW gas project in Delaware County, PA. The filing names Linwood II as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of July 30, 2021.
| Queue ID | AD1-097 |
|---|---|
| Project name | Phillips Island CT1, CT2, CT3, and ST4 |
| Status (as published) | In Service |
| Substation | Linwood II |
| Point of interconnection | Linwood 230 kV II |
| County | Delaware |
| State | PA |
| Voltage | 230 kV |
| Capacity | 34.8 MW |
| Resource (as published) | Natural Gas |
| Resource category | Gas (normalized for filtering) |
| Target commercial operation | 2021-07-30 |
| Source dataset | serial |
Same substation and county
Delaware, PA: 27 requests in the PJM queue, 12 active totaling 934.7 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 67 |
| MW capacity | 34.8 |
| MFO | 919 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.