Substation Scout

Cushaw Hydropower Station

PJM queue ID AD1-084

Cushaw Hydropower Station (AD1-084) is listed in the PJM interconnection queue as a 5.5 MW hydro project in Bedford County, VA. The filing names Cushaw as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of January 15, 2019.

Queue IDAD1-084
Project nameCushaw Hydropower Station
Status (as published)In Service
SubstationCushaw
Point of interconnectionCushaw 115 kV
CountyBedford
StateVA
Voltage115 kV
Capacity5.5 MW
Resource (as published)Hydro
Resource categoryHydro (normalized for filtering)
Target commercial operation2019-01-15
Source datasetserial

Same substation and county

Bedford, VA: 8 requests in the PJM queue, 1 active totaling 5.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy5.5
MW capacity5.5
MFO7.5

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first