Substation Scout

Bedford Solar Center

PJM queue ID AD1-033

Bedford Solar Center (AD1-033) is listed in the PJM interconnection queue as a 42 MW solar project in City of Chesapeake, VA. The filing names Fentress-Landstown as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 1, 2021.

Queue IDAD1-033
Project nameBedford Solar Center
Status (as published)In Service
SubstationFentress-Landstown
Point of interconnectionFentress-Landstown 230 kV
CountyCity of Chesapeake
StateVA
Voltage230 kV
Capacity42 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2021-12-01
Source datasetserial

Same substation and county

City of Chesapeake, VA: 50 requests in the PJM queue, 10 active totaling 1,016 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy70
MW capacity42
MFO70

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first