Substation Scout

Cedar Creek Solar

PJM queue ID AC1-091

Cedar Creek Solar (AC1-091) is listed in the PJM interconnection queue as a 7.5 MW solar project in New Castle County, DE. The filing names Cedar Creek I as its point of interconnection. PJM lists its status as “Suspended”, with a target commercial operation date of May 30, 2027.

Queue IDAC1-091
Project nameCedar Creek Solar
Status (as published)Suspended
SubstationCedar Creek I
Point of interconnectionCedar Creek 138kV I
CountyNew Castle
StateDE
Voltage138 kV
Capacity7.5 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2027-05-30
Source datasetserial

Same substation and county

Cedar Creek I substation: 2 requests in the PJM queue, 2 active totaling 15.1 MW.

Queue IDProjectMWResourceStatus
AC2-184Cedar Creek Solar7.6SolarSuspended

New Castle, DE: 65 requests in the PJM queue, 31 active totaling 1,405.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy19.8
MW capacity7.5
MFO19.8

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.