Substation Scout

Big Plain

PJM queue ID AC1-078

Big Plain (AC1-078) is listed in the PJM interconnection queue as a 66 MW solar project in Madison County, OH. The filing names Beatty-London as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of August 31, 2023.

Queue IDAC1-078
Project nameBig Plain
Status (as published)In Service
SubstationBeatty-London
Point of interconnectionBeatty-London 138kV
CountyMadison
StateOH
Voltage138 kV
Capacity66 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2023-08-31
Source datasetserial

Same substation and county

Beatty-London substation: 3 requests in the PJM queue, 2 active totaling 79.2 MW.

Queue IDProjectMWResourceStatus
AD1-081Big Plain 213.2SolarIn Service
AI2-392Beatty-London 138 kV31.7SolarWithdrawn

Madison, OH: 40 requests in the PJM queue, 11 active totaling 3,530 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy176
MW capacity66
MFO176

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.