Egypt Road Solar
PJM queue ID AB2-136
Egypt Road Solar (AB2-136) is listed in the PJM interconnection queue as a 24.8 MW solar project in Dorchester County, MD. The filing names Cambridge-West Cambridge as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 31, 2025.
| Queue ID | AB2-136 |
|---|---|
| Project name | Egypt Road Solar |
| Status (as published) | In Service |
| Substation | Cambridge-West Cambridge |
| Point of interconnection | Cambridge-West Cambridge 69kV |
| County | Dorchester |
| State | MD |
| Voltage | 69 kV |
| Capacity | 24.8 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2025-12-31 |
| Source dataset | serial |
Same substation and county
Dorchester, MD: 44 requests in the PJM queue, 8 active totaling 105.7 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 51.1 |
| MW capacity | 24.8 |
| MFO | 51.1 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.