Substation Scout

Blooming Grove WF

PJM queue ID AB2-047

Blooming Grove WF (AB2-047) is listed in the PJM interconnection queue as a 32.5 MW wind project in McLean County, IL. The filing names Brokaw-Pontiac Midpoint as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 30, 2020.

Queue IDAB2-047
Project nameBlooming Grove WF
Status (as published)In Service
SubstationBrokaw-Pontiac Midpoint
Point of interconnectionBrokaw-Pontiac Midpoint
CountyMcLean
StateIL
VoltageNot reported
Capacity32.5 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Target commercial operation2020-12-30
Source datasetserial

Same substation and county

Brokaw-Pontiac Midpoint substation: 4 requests in the PJM queue, 1 active totaling 32.5 MW.

Queue IDProjectMWResourceStatus
AD2-153Brokaw-Pontiac Midpoint26.4WindWithdrawn
AD2-154Brokaw-Pontiac Midpoint26.4WindWithdrawn
AD2-155Brokaw-Pontiac Midpoint26.4WindWithdrawn

McLean, IL: 41 requests in the PJM queue, 15 active totaling 1,021.9 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy250
MW capacity32.5
MFO250

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.