Union Bridge Solar Facility
PJM queue ID AB1-096
Union Bridge Solar Facility (AB1-096) is listed in the PJM interconnection queue as a 3.1 MW solar project in Carroll County, MD. The filing names Carroll-Mt. Airy as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of February 28, 2022.
| Queue ID | AB1-096 |
|---|---|
| Project name | Union Bridge Solar Facility |
| Status (as published) | In Service |
| Substation | Carroll-Mt. Airy |
| Point of interconnection | Carroll-Mt. Airy 34.5kV |
| County | Carroll |
| State | MD |
| Voltage | 34.5 kV |
| Capacity | 3.1 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2022-02-28 |
| Source dataset | serial |
Same substation and county
Carroll, MD: 4 requests in the PJM queue, 3 active totaling 9.1 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 8.166 |
| MW capacity | 3.134 |
| MFO | 8.166 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.