Cooper Solar

PJM queue ID AB1-063

Cooper Solar (AB1-063) is listed in the PJM interconnection queue as a hybrid request filed at 0 MW (a net change or energy-only filing) in Camden County, NJ. The filing names Locust St. as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 1, 2016.

Queue IDAB1-063
Project nameCooper Solar
Status (as published)In Service
SubstationLocust St.
Point of interconnectionLocust St. 13kV
CountyCamden
StateNJ
Voltage13 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Solar; Storage
Resource categoryHybrid (normalized for filtering)
Target commercial operation2016-12-01
Source datasetserial

Same substation and county

Camden, NJ: 46 requests in the PJM queue, 10 active totaling 310.1 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy0.4
MW capacity0
MFO0.4

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.