Springdale 1 & 2 (A59_W00) is listed in the PJM interconnection queue as a 88 MW gas project in Allegheny County, PA. The filing names Springdale as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of December 1, 2000.

Queue IDA59_W00
Project nameSpringdale 1 & 2
Status (as published)In Service
SubstationSpringdale
Point of interconnectionSpringdale 138 kV
CountyAllegheny
StatePA
Voltage138 kV
Capacity88 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2000-12-01
Source datasetserial

Same substation and county

Springdale substation: 4 requests in the PJM queue, 2 active totaling 613 MW.

Queue IDProjectMWResourceStatus
B18_W03Springdale CT3, CT4, ST5525GasIn Service
V1-013Springdale 138kV580CoalWithdrawn
AH1-562Springdale Battery Storage II250BatteryWithdrawn

Allegheny, PA: 64 requests in the PJM queue, 11 active totaling 1,589.8 MW.

A substation with the same name is named in PJM transmission planning materials: Springdale (APS, 12 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy96
MW capacity88
MFO96

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first