Wicomico, MD interconnection queue

7 active projects totalling 175.5 MW in the PJM queue, plus 27 with terminal status (shown greyed).

7active projects
175.5active MW
34total filed
Queue IDProjectkVMWResourceStatus
C01-2002 Walston Switch - New Hope 69 kV 69 130 Battery Active
Z2-071 Piney Grove-New Church 138kV 138 55 Not reported Withdrawn
AH2-198 Mt. Hermon 69 kV 69 53.8 Solar Withdrawn
AC2-023 Porter Mill Solar 69 26.5 Solar Suspended
Y3-110 North Salisbury-Worcester 69kV 69 15.7 Other Withdrawn
AB2-180 Hebron Solar 69 14 Solar Withdrawn
AH1-039 Mt. Hermon 23 kV 23 12 Solar Withdrawn
AB2-095 Ocean Pines-Walston Switch 69kV 69 11.4 Solar Withdrawn
AA1-142 Vienna-Laurel 69kV 69 7.6 Solar Withdrawn
W1-070 Laurel 69kV 69 7.6 Solar Withdrawn
W3-037 Delmar 12kV 12 7.6 Solar Withdrawn
X4-017 Fruitland 69kV 69 7.6 Solar Withdrawn
O25 Newland Park LF 25 6 Gas In Service
Y1-087 New Hope n/r 5.7 Solar Withdrawn
Y3-058 Rockfish Solar Power Plant 69 5.7 Solar In Service
AI2-207 Rockawalkin 69 kV 69 5.4 Solar Withdrawn
AG1-397 Walston Solar 12 4.2 Hybrid Withdrawn
AC1-028 North Salisbury 25kV 25 3.8 Other Withdrawn
W4-096 Piney Grove 25kV 25 3.8 Solar Withdrawn
AG2-115 Mt. Hermon 25 kV 25 3.6 Solar Withdrawn
AF2-248 Edgewood 12 kV I 12 3.4 Solar Withdrawn
AF1-258 Hebron Solar 69 3.2 Solar In Service
AH1-057 Edgewood 12.47 kV 12.5 3 Solar Active
AB2-166 Aydelotte Solar Project 12 2 Solar Withdrawn
AD1-095 North Salisbury 25 kV 25 2 Gas Withdrawn
AC1-050 Mardela Springs 12 1.9 Solar Withdrawn
W3-036 Pemberton 12kV 12 1.9 Solar Withdrawn
AF2-250 Kumquat Solar 12 1.1 Solar In Service
AF2-249 Citron Storage 12 0.6 Battery Withdrawn
AG2-274 Hebron 69 kV II 69 0 Solar Withdrawn
AH2-053 Mardela Springs 12.47 kV 12.5 0 Solar Withdrawn
AH2-054 Edgewood 12.47 kV I 12.5 0 Solar Withdrawn
AH2-070 Edgewood 12.47 kV II 12.5 0 Solar Withdrawn
AH2-071 Edgewood 12.47 kV III 12.5 0 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.