Fulton, PA interconnection queue

2 active projects totalling 57.5 MW in the PJM queue, plus 15 with terminal status (shown greyed).

2active projects
57.5active MW
17total filed
Queue IDProjectkVMWResourceStatus
H27_W72 McConnellsburg-Cherry Run 138 kV 138 350 Gas Withdrawn
H27_W71 McConnellsburg-Guilford 138 kV 138 252 Gas Withdrawn
AH2-231 Not reported n/r 125 Battery Withdrawn
AE1-132 McConnellsburg 138 kV 138 51 Solar Withdrawn
AC1-211 McConnellsburg 138kV 138 48.1 Solar Withdrawn
AD2-009 Great Cover Solar LLC 138 48.1 Solar In Service
AF2-117 Spring Run Solar 138 46.7 Solar Withdrawn
AI2-297 McConnellsburg 138 kV 138 18.4 Solar Withdrawn
AF2-116 Great Cove Solar 138 13.3 Solar Withdrawn
AF1-136 FU-Hanks Solar 34.5 9.4 Solar Engineering and Procurement
W4-042 Cove Creek Solar Project 34.5 7.6 Solar Withdrawn
Q05 Emmaville Mountain n/r 5 Wind Withdrawn
Q06 Breezewood n/r 5 Wind Withdrawn
Q07 DuVall South n/r 5 Wind Withdrawn
AH1-194 Warfordsburg – Hancock 34.5 kV 34.5 2.6 Solar Withdrawn
AH2-037 Booth 12.47 n/r 0 Solar Withdrawn
AH2-110 Wells - Harrington 69 kV 69 0 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.