Benton, IN interconnection queue
4 active projects totalling 238.7 MW in the PJM queue, plus 7 with terminal status (shown greyed).
4active projects
238.7active MW
11total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AH1-596 | Fowler Ridge 345 kV | 345 | 125 | Battery | Withdrawn |
| Q01 | Fowler Ridge WF | 345 | 100 | Wind | In Service |
| AH1-595 | Fowler Ridge 345 kV | 345 | 96.6 | Solar | Withdrawn |
| AD1-137 | Dequine 345 kV | 345 | 65 | Wind | Withdrawn |
| AD2-015 | Dequine 345 kV | 345 | 65 | Wind | Withdrawn |
| Q03 | Fowler Ridge 4 WF | 345 | 50 | Wind | In Service |
| C01-1575 | Fowler 345kV 345 kV | 345 | 48.7 | Wind | Active |
| T126 | Meadow Lake WF II, Meadow Lake WF III | 345 | 40 | Wind | In Service |
| U1-087 | Dequine 345kV | 345 | 19.5 | Wind | Withdrawn |
| U1-088 | Dequine 345kV | 345 | 13 | Wind | Withdrawn |
| AE1-002 | Wilton Center-Loretto | n/r | 0 | Battery | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.