Benton, IN interconnection queue

4 active projects totalling 238.7 MW in the PJM queue, plus 7 with terminal status (shown greyed).

4active projects
238.7active MW
11total filed
Queue IDProjectkVMWResourceStatus
AH1-596 Fowler Ridge 345 kV 345 125 Battery Withdrawn
Q01 Fowler Ridge WF 345 100 Wind In Service
AH1-595 Fowler Ridge 345 kV 345 96.6 Solar Withdrawn
AD1-137 Dequine 345 kV 345 65 Wind Withdrawn
AD2-015 Dequine 345 kV 345 65 Wind Withdrawn
Q03 Fowler Ridge 4 WF 345 50 Wind In Service
C01-1575 Fowler 345kV 345 kV 345 48.7 Wind Active
T126 Meadow Lake WF II, Meadow Lake WF III 345 40 Wind In Service
U1-087 Dequine 345kV 345 19.5 Wind Withdrawn
U1-088 Dequine 345kV 345 13 Wind Withdrawn
AE1-002 Wilton Center-Loretto n/r 0 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.