Tap Wolf (#) - Reiter Switch (#) Ckt1 substation interconnection queue
2 active projects totalling 487.9 MW in the ERCOT queue.
2active projects
487.9active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 28INR0323 | Velociraptor BESS II | 345 | 246.1 | Battery | SS Completed, FIS Started, No IA |
| 28INR0322 | Velociraptor Solar II | 345 | 241.8 | Solar | SS Completed, FIS Started, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.