Tap Twin Oak - TNP One substation interconnection queue

2 active projects totalling 407.2 MW in the ERCOT queue.

2active projects
407.2active MW
2total filed
Queue IDProjectkVMWResourceStatus
22INR0503 Tidwell Prairie II Batt 345 203.6 Battery SS Completed, FIS Completed, IA
22INR0504 Barton Branch IA 345 203.6 Battery SS Completed, FIS Completed, IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.