Tap Riley - West Krum ckt 1 substation interconnection queue
2 active projects totalling 1,107.3 MW in the ERCOT queue.
2active projects
1,107.3active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 23INR0228 | Hiru Solar | 345 | 603.7 | Solar | SS Completed, FIS Started, No IA |
| 24INR0444 | Hiru Storage | 345 | 503.6 | Battery | SS Completed, FIS Started, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.