Tap Nacogdoches SE - Mt Enterprise substation interconnection queue

2 active projects totalling 301.5 MW in the ERCOT queue.

2active projects
301.5active MW
2total filed
Queue IDProjectkVMWResourceStatus
26INR0161 Timberline Solar 345 201 Solar SS Completed, FIS Started, No IA
26INR0162 Timberline Storage 345 100.5 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.