Tap Mustang Prairie - Latexo substation interconnection queue
2 active projects totalling 230.6 MW in the ERCOT queue.
2active projects
230.6active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| 26INR0176 | Dionysus Solar | 138 | 153.3 | Solar | SS Completed, FIS Started, No IA |
| 26INR0177 | Dionysus Storage | 138 | 77.3 | Battery | SS Completed, FIS Started, No IA |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.