Houston, TX interconnection queue

8 active projects totalling 1,628.9 MW in the ERCOT queue.

8active projects
1,628.9active MW
8total filed
Queue IDProjectkVMWResourceStatus
24INR0420 Camino Ranch Storage SLF 138 298.1 Battery SS Completed, FIS Completed, IA
24INR0412 Camino Ranch Solar SLF 138 296.4 Solar SS Completed, FIS Completed, IA
26INR0257 Camino Ranch Storage 2 SLF 138 238.5 Battery SS Completed, FIS Completed, IA
26INR0256 Camino Ranch Solar 2 SLF 138 237.2 Solar SS Completed, FIS Completed, IA
26INR0363 Saint Charles Energy Storage 138 202.7 Battery SS Completed, FIS Started, No IA
26INR0176 Dionysus Solar 138 153.3 Solar SS Completed, FIS Started, No IA
27INR0196 Houston County BESS 138 125.4 Battery SS Completed, FIS Started, No IA
26INR0177 Dionysus Storage 138 77.3 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.